Power Today |
 
Advertise Here [728 W x 90 H pixels]
Communication Feature | September 2015

Reduction of auxiliary power consumption using CFD techniques

Introduction
In a thermal power plant, hot flue gases along with ash containing quartz and mullite (abrasive) particles leave through the Economizer (ECO) outlet, pass through the Regenerative Air Pre-heater (RAPH), flue gas duct, Electrostatic Precipitator (ESP), Induced Draught (ID) Fan and Stack. Flue gas distribution along the duct cross sectional area is usually non-uniform. Hence, requiring proper study of the flue gas path. CFD technique has emerged as one of the most economic methods to analyse various equipments in power plants and can be used to validate various design parameters.

Issues in flue gas ducting - Air Pre-Heater outlet to induced draft fan inlet

  • Uneven flow distribution through the ducts and ESP.
  • High auxiliary power consumption.
  • Very high turbulent flow regimes.
  • Recirculation zones.
  • Ash accumulations.
  • High pressure drop across ducts.
  • Erosion effects and other various parameters.

The CFD technique is best explained by a real case analysis. accordingly the following case is presented to showcase the usefulness of CFD as a tool.

Real Case Analysis
One of the Jindal Power Ltd´s, Raigarh unit with load of 250 MW power plant was facing all the above mentioned generalised issues. Various input data was collected from the client for problematic areas, including existing operating parameters. As a first step of CFD, based on the data a 3D model was developed in Ansys Work bench (Refer Fig 1).

Confirmation of model was done mutually between plant and CFD Experts. A mesh (model was divided into millions of minute elements) was developed in ANSYS ICEM CFD, and numerical algorithm representing various mathematical differential equations related to flow conditions were applied to this meshed model. Boundary conditions were provided as input to these meshes to stimulate ´AS IS CONDITION (Existing)´ of the running pant in CFX/Fluent. A base case analysis was done to confirm to all the existing problematic areas.

Once the problems were identified, further iterative analysis was done to optimise the possible solutions. Accordingly, a number of suggestions with their benefits were given to the client and to check the site feasibility. The general modification covered inclusion of diverter plates to uniformly distribute the flow, and removal of sharp corners was also proposed to avoid direct impact on duct surface and thus reduce erosion. Engineering drawings related to modifications were submitted to the client after they accepted the modifications. The supply and erection of these modifications were carried out on approval. The post-installation benefits were evolved by measuring various parameters like pressure drop reduction, ID fan current reduction, duct erosion reduction etc.

CONCLUSION
The inference that can be drawn from the CFD analysis done in Jindal power plant, is that the problems of existing duct like unequal flow andl flow concentration inside the duct, causing the high erosion of the duct at particular locations, high turbulence, flow separation and re-circulation zone which caused high pressure drop in the ducting, were resolved.

By designing the optimised guide vanes using CFD, the flow was nearly uniform with optimum turbulence and completely avoiding re-circulation zones. After modification, the total pressure drop reduction from AH outlet to ID fan inlet was 30 mm WC, which reduced the load on the ID Fan. It was also observed that at the ESP inlet duct, flow had been balanced in all pass of the ESP, which resulted in increased efficiency of ESP.

BENEFITS

  • Improved duct design to ensure proper flow distribution across the duct.
  • Reduction in high velocity and turbulence will reduce erosion of ducts.
  • Velocity of flue gases is within the specified range.
  • Reduced draft loss.
  • Reduced pressure drop.
  • Lower turbulence level (smooth flow).
  • Decreased amount of ash settling in the duct.
  • Minimised erosion effect of ash.
  • High auxiliary power saving of ID fans.

Paper presented by CAE - R&D Center, Mechwell Industries Nashik, India

Post your comment
Name:  
Email:    
Comments:  
Verification Code:   Change Image

 

Posted Comment
1 .     Yogesh Says:
17 Oct 2016
I wish to start pvc / pp electric wire unit in Delhi. What kind of information I can get if I subscribe for your magazine

2 .     Sarfaraj Bilakhiya Says:
20 Sep 2016
Pls invite me all auction in gujarat

3 .     k.natarajan Says:
20 Jun 2016
we are doing business developing for solar power ,thermal power , customer supporting and we have 45 mw splar power on hand needs investors..... thanks lot pls call +910842559230 +919842753550


Advertise Here [728 W x 90 H pixels]