Delay drains out energy
Now let´s take stock of sector-wise performance of projects, their cost overrun and reasons. To start with, both projects in the atomic energy sector are delayed. During the month, project ´Prototype Fast Breeder Reactor´ (Bhavini, 500 MWE), has reported additional delay of18 months due to logjam in delivery of certain critical items on account of longer (than expected) time taken for rigorous testing and qualification.
Rahul Kamat, Prototype Fast Breeder Reactor, Bhavini, NPCIL, Mospi, Energy, ISPRL, Barh STPP, Prabati HEP, Koldam HEP, Bongaigaon Thermal Power, Tuticorin Thermal Power Project, SCCL, ´Adriyala Shaft Project, Geo-Mining
|
Exploring strategic reserves
The Government of India (GoI) had in 2004 decided to set up 5 million metric tons of strategic crude oil storages at Visakhapatnam, Mangalore and Padur, in order to ensure energy security, which in addition to the existing storages of crude oil and petroleum products with oil companies, serve as a cushion in response to external supply disruptions.
|